HINKLEY — Terra-Gen celebrated its new $950 million solar installation on Nov. 10 with a ribbon-cutting and speeches on land that was once home to part of the earliest and largest solar energy generating plants in the world.
Lockhart Solar and Storage complex in northwestern San Bernardino County can supply electricity for roughly 350,000 homes and businesses with 365MW of solar plus 173.7 MW of battery storage, the company said. The earliest phases of the project began commercial operation in 2023, with the battery storage and final phase of solar going online earlier this year.
Simon Day, vice president and head of solar development at Terra-Gen, noted that the site at Harper Dry Lake had been part of California’s solar industry for decades and before that was agricultural land — Lockhart Farms.
“In the mid-1980s it became home to SEGS VIII and IX, part of an early generation of large-scale solar thermal power plants known as the Solar Electric Generating Stations, or SEGS,” Day said. “Those facilities used mirrors to concentrate the sun’s rays, heat a fluid and produce steam to generate electricity. They helped establish that solar power could operate at utility scale, and they supplied electricity to the grid for decades.”
The first of the SEGS plants was located in Daggett, about 22 miles east of Hinkley, and went online in 1984. Ten SEGS plants were planned by Luz International Limited, also known as Luz Industries, but the company filed for bankruptcy in late 1991 after failing to secure construction financing for the tenth facility and losing key tax incentives, according to multiple reports.
In December 1997, according to a U.S. Department of Energy website, the nine SEGS plants developed by Luz had a combined rated capacity of 354 MWe — more than 90% of the solar electric generation in the entire world at the time.
State documents show that Terra-Gen acquired SEGS VIII and IX facilities by early 2018, eventually decommissioning the thermal solar installations and beginning development of the modern facility.
Terra-Gen CEO John O’Connor made note of the site’s heritage in a comment about his first visit there, soon after joining the company.
“I was really blown away by the vast array of mirrors spread out over this site, and by the fact that they had been generating renewable power for decades before I stood there in 2009,” he said. “At that time, utility-scale renewable energy was just beginning to gain momentum, and these facilities had operated for decades. That left a substantial impression on me, but I had no idea what was to come.
“Now here we are, almost two decades later, and thanks to the creative planning and years of hard work by this team and our partners, the Lockhart Solar and Storage facilities have become a reality, ensuring renewable energy will continue to be generated on this site for decades to come.”
Day noted that the history matters.
“The people who built and operated those plants developed knowledge, infrastructure and experience that we have been able to build upon,” he said.
He referred to the experience Robert Fimbres, Lockhart’s general manager, “whose experience in solar goes back to those original SEGS projects, including directly helping build SEGS VIII and IX right here more than 40 years ago.
“Robert represents a remarkable continuity between the early days of this industry and the facilities we’re celebrating today,” Day continued. “The technology has changed enormously over that time, but the need for capable, committed people has remained the same.”
O’Connor recalled the mirrors used at the SEGS installations and Day referred to the First Solar photovoltaic modules visible in the background during the ribbon-cutting event and Nextpower trackers.
“The scale of the construction effort also deserves a moment,” he said.
“Across Lockhart 1 through 4, more than 925,000 solar modules were installed. During one particularly productive week on Lockhart 3, crews installed nearly 48,000 panels. Anyone who has managed a construction schedule will appreciate the planning, coordination and sheer effort behind that number.
“The battery facilities include 248 individual storage containers,” he continued. “Across solar, storage and high-voltage work, construction created more than 1,000 union jobs and involved over 880,000 work hours. Altogether, nearly $950 million went into financing and building this complex across its phases. Over the life of the facilities, we expect them to contribute more than $40 million in local property taxes. Those are meaningful investments in San Bernardino County.”
Because Lockhart went online earlier this year — before a property tax exemption is expected to expire at the end of 2026 — the value of the solar installation will not be assessed for property tax. Following the ribbon-cutting, Day explained that the battery installations are not exempt and that’s why the property is expected to pay $40 million in property tax over its life.
During his presentation, Day noted that Lockhart is home to Terra-Gen’s remote operations center, employing 14 people and supporting the company’s wider energy business. He said an additional 10 people work there in operations, maintenance and administrative roles.
Representing the state was Rohimah Moly, deputy director of Energy and Climate at the Governor’s Office of Business and Economic Development.
She noted that by the end of September, the state had added more than 37,000 MW of clean energy to the grid, mostly from solar and battery energy projects.
“As California continues to deploy new, clean and critical power infrastructure in pursuit of our climate and energy goals, this project demonstrates the leadership and the type of partnership between stakeholders, businesses and governmental entities that is necessary to bring the state closer to our carbon neutrality goals,” Moly said.
Ribbon-cutting
The day’s events included comments from Barstow Mayor Timothy R. Silva and presentations from elected officials.
Silva said he grew up in Hinkley and believes it’s the perfect location for solar energy.
“I drove in here this morning. This is way, way out,” he said. “As I passed the power lines I was saying, ‘this is perfect. This is a perfect location.’
“We can give you sun,” the mayor continued. “I can guarantee, most years, 364 and a half days a year. So, this is the right place for this, and I’m really excited.”
Sam Sours, vice president of solar development for Terra-Gen, acted as emcee for the event and introduced representatives of elected officials who presented certificates prior to the ribbon-cutting event. These included Corrine Mora, field rep for Rep. Jay Obernolte, (R-Hesperia),
Angela Allen, senior field rep for Assemblyman Tom Lackey, (R-Palmdale) and Samuel Shoup, constituent services director for San Bernardino County First District Supervisor Paul Cook.
In addition to Fimbres and some of the speakers, participants in the ribbon-cutting included Roy Xu, senior director power resources at WestLight Energy, Jeffrey White, senior manager power resources at WestLight Energy, Julie Furber, manager director of Igneo Infrastructure Partners and Terra-Gen board member and Michael Freeman, principal manager at Southern California Edison.
About Terra-Gen
Terra-Gen is owned by Abu Dhabi Future Energy Company PJSC – Masdar and Igneo Infrastructure Partners. More information about the company is online at terra-gen.com.
Claudia Elliott is editor and founder of The Mojave Beat. She can be reached by email: claudia@mojavebeat.news.